Goldsworth School

Work was completed at Goldsworth School in woking, Surrey in December 2011. Having dug out the existing slab floor, weedkiller was applied to clear the excavated area.

A New ACO Raindrain channel drainage system was installed & linked into the existing surface water manhole.

A terram Geotextile membrane was applied to the surface area and backfilled with 150mm of Type 1 stone, which was compacted with a 10-tonne roller.

Black 'Safetyfall' surfacing was laid & incorporated various colour stencils, including Yellow & Blue splashes, an orange 'Sally the Snake' and a 'Christopher Crocodile with footprints'.

Goldsworth 1Goldsworth 2Goldsworth 3

An smaller area was also laid with Astroturf.

Goldsworth 4

 

 

Linden Bridge School

Work began at Linden Bridge School on the 13th February 2012 and took 3 weeks to complete. The existing tarmac, wet pour-rubber & paving of the old playground area was excavated & removed from site.

After applying weedkiller, all ironwork was adjusted & new square-top edgings were installed. A layer of terram geo-textile membrane was applied to the whole area & a layer of type 1 stone laid.

Once the stone had been compacted, the two-layered safetyfall rubber surface was installed. This consisted of a 50mm SBR Base layer.

Linden Bridge 1 Linden Bridge 2

A layer of EPDM Wearing top 30mm thick was laid.

Linden Bridge 3  Linden Bridge 4 

Yellow tramlines were also applied.

Linden Bridge 5

Linden Bridge 6 

  

 

 

Croydon - Tramlink

London Surfacing were heavily involved in TFL's Tramlink improvement project for Croydon in February 2012 in conjunction with Volkerrail.

Starting in the early hours of Saturday 11th Feb, London Surfacing planed off the existing tarmac surface at different locations within the Croydon Tramlink route - Station Road (Just past West Croydon Bus terminal) & George Street (Crown Hill).

Tramlink 1Tramlink 2

 The base course was laid (20mm binder)

Tramlink 3

14mm Stone Mastic Asphalt was hand laid as surface course at both locations.Red SMA was used at Station Road.

Tramlink 7Tramlink 6

The traditional black was laid at George Street. After being compacted with a Roller the lines were laid in yellow thermoplastic paint.

Tramlink 5Tramlink 4Tramlink 8

The resurfacing & linemarking was completed on the 16th Feb, ready for the handover to TFL the following morning.